Sika MonoTop®-1010
Cement-based reinforcement corrosion protection and bonding primer containing recycled raw materials
Sika MonoTop®-1010 is a one-part, cementitious, polymer-modified coating material. It is used as reinforcement corrosion protection and as a bonding primer. It contains corrosion inhibitors and recycled raw materials, resulting in a lower carbon footprint than a comparable mortar of equal performance.
- Uses recycled raw materials
- Easy to use, just mix with water
- Good adhesion to concrete and steel
- Good resistance to water and chloride penetration
- Applied with a brush or by wet spray equipment
Find this product in your country
Overview
Areas of Application
As part of a concrete repair system, Sika MonoTop®-1010 is used as:- Reinforcement corrosion protection
- Bonding primer on concrete surfaces
- Control of anodic areas (Principle 11, method 11.1 of EN 1504-9), by treating the surface of the reinforcement to prevent corrosion
- The Product may only be used by experienced professionals.
Advantages
- Uses recycled raw materials
- Easy to use, just mix with water
- Good adhesion to concrete and steel
- Good resistance to water and chloride penetration
- Applied with a brush or by wet spray equipment
Packaging
Standard bag | 12 kg plastic pail and 25 kg paper bag |
Refer to the current price list for available packaging variations.
Color
Grey
Product Details
SUSTAINABILITY
Contributes towards satisfying Materials and Resources (MR) Credit: Building product disclosure and optimization — Environmental Product Declarations under LEED® v4 — 1 point
Contributes towards satisfying Materials and Resources (MR) Credit: Building Product Disclosure and Optimization — Sourcing of Raw Materials under LEED® v4 — 1 point
Contributes towards satisfying Materials and Resources (MR) Credit: Building Product Disclosure and Optimization — Material Ingredients under LEED® v4 — 1 point
LEED Attestation, Sika MonoTop-1010, Eurofins, Test Report No. 392-2025-00352801_H_EN
Specific Environmental Product Declaration (EPD) in accordance with EN 15804. EPD independently verified by BRE Global
CERTIFICATES AND TEST REPORTS
CE marking and declaration of performance based on EN 1504-7:2006 Products and systems for the protection and repair of concrete structures — Reinforcement corrosion protection
Tensile bond strength after vibrational stress DAfStb guideline, Sika MonoTop-4012, kiwa, Test report No. P 11864-1-E
Initial testing on corrosion protection acc. EN 1504-7 en_AT
Composition
Portland cement, cement replacement, re-dispersible polymer powder, selected aggregates and additives
Shelf life
Standard bag | 12 months from date of production |
Storage conditions
The Product must be stored in original, unopened and undamaged packaging in dry conditions at temperatures between +5 °C and +35 °C. Always refer to the packaging.
Refer to the current Safety Data Sheet for information on safe handling and storage.
Soluble chloride ion content
≤ 0.01 % | (EN 1015-17) |
System structure
Sika MonoTop®-1010 is a reinforcement corrosion protection primer in accordance with EN 1504-7 as part of the Sika® repair system. It is the first component of the system, followed by the application of Sika MonoTop® or SikaEmaco® concrete repair mortars.
Compressive strength
Cured 28 d at +21 °C | 50 MPa |
Tensile adhesion strength
≥ 2.0 MPa | (EN 1542) |
Diffusion resistance to water vapour
100 µH2O | (DIN EN ISO 12572) |
Corrosion test
Pass | (EN 15183) |
Diffusion resistance to carbon dioxide
1200 µCO2 | (EN 1062-6) |
Application
Mixing ratio
Machine-applied | 5.0 L per 25 kg bag (20 % water addition) |
Brush-applied | 5.25 L per 25 kg bag (21 % water addition) |
Layer thickness
Reinforcement corrosion protection | Minimum 2 mm |
Bonding primer | Sufficient to coat the concrete surface in a thin layer, filling pores and voids |
Material temperature
Maximum | +30 °C |
Minimum | +5 °C |
Ambient air temperature
Maximum | +30 °C |
Minimum | +5 °C |
Substrate temperature
Maximum | +30 °C |
Minimum | +5 °C |
Pot Life
Application | Water addition | Time at +20 °C |
Machine applied | 20 % | 90 minutes |
Brush applied | 21 % | 120 minutes |
Waiting time to overcoating
Apply concrete repair mortar wet on wet onto bonding primer.
Apply concrete repair mortar wet on dry onto reinforcement corrosion protection.
Fresh mortar density
2.0 kg/l | (EN 1015-6) |
Consumption
AS REINFORCEMENT CORROSION PROTECTION
For a total layer thickness of 2 mm, in two layers of 1 mm thickness each:
Rebar diameter | Amount of powder per metre |
8 mm | 100 g/m (50 g/m per layer) |
16 mm | 200 g/m (100 g/m per layer) |
AS BONDING PRIMER ON MINERAL SURFACES
1.5–2.0 kg powder per m² and mm layer thickness, depending on substrate conditions
Note: Consumption data is theoretical and does not allow for any additional material due to surface porosity, surface profile, variations in level, wastage or any other variations. Apply the Product to a test area to calculate the exact consumption for the specific substrate conditions and proposed application equipment.
Yield
Fresh material per standard bag | 14.3 L |
Note: Consumption data is theoretical and does not allow for any additional material due to surface porosity, surface profile, variations in level, wastage or any other variations. Apply the Product to a test area to calculate the exact consumption for the specific substrate conditions and proposed application equipment.
SUBSTRATE PREPARATION
CONCRETE
- Clean the substrate thoroughly so it is free from dust, loose material, surface contamination and material which reduces adhesion, prevents suction or wetting by the repair materials.
- Remove delaminated, weak, damaged and deteriorated concrete, and where necessary, sound concrete. Remove using mechanical hand-held tools, high or ultra-high-pressure water blasting equipment.
- Remove sufficient concrete from around corroded reinforcement to allow cleaning, application of a corrosion protection coating (where required) and compaction of the concrete repair mortar.
4. Prepare repair surface areas in simple square or
rectangular layouts to avoid shrinkage stress con-
centrations and cracking while the repair material
cures. This can also avoid structural stress concen-
trations from thermal movement and loading during
the service life.
STEEL REINFORCEMENT
- Remove rust, scale, mortar, concrete, dust and other loose and deleterious material which reduces bond or contributes to corrosion.
- Prepare surfaces to bright steel, Sa 2 (ISO 8501-1), using abrasive blast cleaning or high-pressure water blasting equipment.
PRE-WETTING
Sufficient saturation of the concrete substrate prior to application enables the mortar to gain its full mechanical properties.
- Thoroughly pre-wet the prepared concrete substrate for a minimum of 2 hours before application.
- Keep the surface wet and do not allow to dry.
- The final pre-wetted surface must achieve a dark matt appearance (saturated surface dry).
MIXING
- Pour the minimum specified quantity of clean water into the mixing vessel.
- Gradually add the powder to the water while stirring slowly.
- Mix for at least for 3 minutes until a uniform, lump-free consistency is achieved.
- If necessary, add small amounts of water, within the allowed range, to adjust consistency. Do not exceed the maximum water content.
- Check the consistency after every mix.
APPLICATION
IMPORTANT
Strictly follow installation procedures
Strictly follow installation procedures as defined in Method Statements, application manuals and working instructions which must always be adjusted to the actual site conditions.
IMPORTANT
Risk of cracking due to application in direct sun or strong winds
- Do not apply the Product in direct sun, strong winds or both.
REINFORCEMENT CORROSION PROTECTION
Preconditions
If using spray equipment, the substrate has been protected from overspray.
- Use a clean brush or spraying equipment to apply a first coat of Sika MonoTop®-1010 1 mm thick to cover the reinforcement bars.
- When the first coat is fingernail-hard, apply a second coat of Sika MonoTop®-1010 1 mm thick.
- Wait until completely dry before applying repair mortar.
BONDING PRIMER
- Remove excess water from within the surface pores and cavities with a clean sponge.
- Use a brush, roller or spray equipment to apply a thin layer of Sika MonoTop®-1010 over the complete substrate surface to fill surface pores or cavities.
- Apply the subsequent layer of repair mortar wet on wet.
CURING TREATMENT
Protect from wind, rain, frost and direct sunlight after application.
CLEANING OF EQUIPMENT
Clean all tools and application equipment with water immediately after use. Hardened material can only be removed mechanically.